Friday, December 11, 2009

Lake George Sewage: DEC Demands Upgrades Costing Millions

New York State has officially closed its investigation of the July 5 sewer break that spilled thousands of gallons of sewage into Lake George and closed Shepard Park Beach to swimmers for the remainder of the summer.

But according to a consent order drafted by the state’s Department of Environmental Conservation, Lake George Village must agree to complete millions of dollars worth of improvements to the Village’s wastewater collection system if it is to avoid $10,000 in fines and other enforcement actions.

The Village’s Board of Trustees has not yet authorized Mayor Bob Blais to sign the consent order, said Darlene Gunther, the Village’s Clerk-Treasurer.

“The board is awaiting notification that the Village has received a grant that will help pay for the improvements, said Gunther.

“Once we receive the grant, we’ll sign it and then go ahead and do everything that is required of us,” said Mayor Blais.

U.S. Senator Kirsten Gillibrand has placed Lake George Village’s wastewater collection system on a list of municipal projects eligible for immediate federal funding, said Blais.

The Village should hear within a matter of days whether it has been awarded the grant, said Gunther.

Lake George Village has also submitted an application for funds that would allow the Village to install equipment at the Wastewater Treatment Plant that would remove nitrogen from effluent, said Blais.

Even if it signs the consent order, Lake George Village will still be required to pay $5000 in fines, but Village officials hope that sum can be reduced through negotiations, said David Harrington, the Village’s Superintendent of Public Works.

In return for agreeing to improve the system, state officials will agree to forego additional enforcement actions against the Village for violating, however inadvertently, state laws prohibiting the discharge of sewage into Lake George, the consent order states.

Among other things, the DEC requires Lake George Village to repair the broken pipe that caused the sewage spill and undertake remedial actions at the pump station in Shepard Park.

According to Harrington, those actions were completed within days of the break.

Crews from Lake George Village’s Department of Public Works and the construction firm TKC completed repairs to the pump station in Shepard Park and a new section of pipe where the break occurred was installed. Village crews also installed additional alarms within the building, said Blais.

The consent order also requires Lake George Village to draft an Asset Management Plan for the wastewater system, which, according to the consent order, must include: “an inventory of all wastewater collection system assets; an evaluation of conditions; a description of necessary repairs or replacements; the schedule for repairs; costs of repairs.”

At its November meeting, the Lake George Village Board of Trustees appropriated $5000 to retain C.T. Male Associates to draft the Asset Management Plan.

According to Blais, C.T. Male associates helped develop the application for the grant that is now pending.

“We were asked by Senator Kirsten Gillibrand’s staff to establish our priorities, and our priority is to slip line every sewer line where there’s a problem with infiltration of water,” said Blais.

“DEC’s priorities, as we understand them, are the priorities we’ve established,” Blais added.

Walt Lender, the Lake George Association’s executive director, said that he had not yet seen DEC’s order of consent and could not comment on its terms.

Peter Bauer, the executive director of The Fund for Lake George, praised the DEC for requiring Lake George Village to complete an Asset Management Plan.

“This is the first step in the prevention of future sewage spills; we need to know where the flaws in the system are, and this will help identify the improvements that must be made if we’re to address the chronically high coliform counts in waters near the Village,” said Bauer.

Dave Harrington estimated the costs of improvements to the wastewater system to be $3.2 million.

DEC’s consent order requires those improvements to be completed by September, 2011.

Photo: Shepard Park in June, before the spill that closed the beach. Lake George Mirror photo.

For more news from Lake George, read the Lake George Mirror. http://lakegeorgemirror.com

Related Stories


Anthony F. Hall

Anthony F. Hall is the editor and publisher of the Lake George Mirror.

Anthony grew up in Warrensburg and after an education that included studying with beat poet Gregory Corso on an island in the Aegean, crewing a schooner in Hawaii, traveling through Greece and Turkey studying Byzantine art and archeology, and a stint at Lehman Brothers, he returned to the Adirondacks and took a job with legendary state senator Ron Stafford.

In 1998, Anthony and his wife Lisa acquired the Lake George Mirror, once part of a chain of weekly newspapers owned by his father Rob Hall.

Established in the 1880s, the Mirror is America’s oldest resort newspaper.





Comments are closed.

Support the Adirondack Almanack and the Adirondack Explorer all year long with a monthly gift that fits your budget.

Support the Adirondack Almanack and the Adirondack Explorer all year long with a monthly gift that fits your budget.